RM820m claims to drive up Bakun Dam costs


File print of Bakun Dam. Picture courtesy of www.bakundam.com
KUALA LUMPUR, May 7 Officially priced during RM7.46 billion, a Bakun hydroelectric dam plan in Sarawak is expected to space station again as contractors explain a whopping RM820 million from a arch promoter, state-owned Sarawak Hidro Sdn Bhd,The Edge Financial Dailyreported today.
However, a final cost for a long-delayed dam plan is nonetheless to be determined.
A joint-venture association led by Sime Darby, a Malaysia-Sino Hydro Corp corner Venture (MCHJV), has put in claims totalling RM670 million for polite functions while an additional consortium of contractors supplying turbines led by Argentina's IMPSA organisation is seeking to explain RM140 million, a every day reported, quoting monetary management team tighten to a project.
It additionally reported government sources familiar with a ongoing negotiations as saying which Sarawak Hidro, a wholly-owned subsidiary of a Finance Ministry, is peaceful to compensate just over RM100 million while a consultants, who were unnamed, disclosed which IMPSA's claims have been rejected.
"Both claims have been still theme to negotiations in between Sarawak Hidro as well as a respective parties. Ultimately a preference will come from a Finance Ministry," a paper reported an unnamed senior building a whole industry senior manager concerned in a plan as saying.
The latest claims come during a time when Sarawak Hidro is desperately seeking for buyers for energy to be generated by a dam, a every day reported.
Rio Tinto, a world's third largest miner, as well as Cahya Mata Sarawak, a monetary as well as building a whole firm formed in Sarawak, announced upon Mar twenty-seven this year they have scrapped skeleton for a US$ 2 billion (RM6.1 billion) aluminiu! m smelte r plan in Sarawak as energy supply conditions could not be finalised.
The aluminium smelter was to have been Bakun's biggest customer,The Edge Financial Dailyreported.
The dam project, first awarded to Ekran Bhd in 1994, was scheduled to have been finished in 2007 but has been plagued by assorted problems including a 1997 Asian monetary crisis.
Inaccurate soil studies by Sarawak Hidro serve difficult polite functions portion of a dam, a commercial operation every day reported.
The huge plan has additionally been downsized, with an undersea cable supplying energy to Peninsular Malaysia scrapped.
Read More @ Source